Friday, 7 Septermber 1990 Washington, DC

1. MIT ASKS NATIONAL SCIENCE BOARD TO RECONSIDER MAGNET DECISION.
The president of MIT, Paul Gray, in a letter to the NSB, charged that the Board was misled by NSF officials. Memoranda from NSF director Erich Bloch and assistant director David Sanchez urged the Board to award the National High Field Magnet Laboratory to Florida State, contrary to recommendations of three peer review panels (WN 24 Aug 90). Gray says the memoranda were incomplete and unbalanced and did not convey to the Board the consequences for US competitiveness in magnet research. David Litster, the director of MIT's Francis Bitter Magnet Laboratory, which has for 30 years been a world class magnet facility, points out in an accompanying letter that the site visit panel concluded that FSU would need five years just to reach the present level of the MIT facility--assuming things go as planned. Moreover, FSU is proposing to purchase its magnets from France. The decision to create the new facility was based on the warning of the 1988 Richardson-Seitz panel that the US was slipping behind Europe and Japan in high magnetic field capability. MIT also claims the cost sharing issue has been distorted, that, in fact, the cost to the NSF would be about the same for the two proposals. The NSB has been an unfailing rubber stamp for Erich Bloch--but Bloch is gone. Nonetheless, few observers believe MIT can win on appeal.

2. PERSISTENT PLUMBING PROBLEMS PLAGUE SHUTTLE MISSIONS.
Columbia is supposed to be at bat, but it sprang another hydrogen leak. If NASA can't fix it pretty soon, it will leave the launch pad sideways. Discovery is on deck, faced with an October launch window for the Ulysses spacecraft--that is, if they can fix the ammonia leak in Discovery's cooling system. Waiting in the hole is Atlantis, which struck out in July with its own hydrogen leak (WN 27 Jul 90). Columbia will conduct observations with the Astro-1, consisting of three UV telescopes that have been delayed since the 1986 Challenger disaster, plus an X-ray telescope. Ulysses, which used to be called International Solar Polar, also dates back to pre-Challenger days. The European-built probe will use the gravity of Jupiter to deflect it out of the ecliptic and into orbit over the poles of the sun. The US was committed to build a second solar explorer, but reneged. Challenger caused NASA to delay Ulysses' launch more than four years. A requirement for future space station crews may be a willingness to fast.

3. IF THIS IS 7 SEPT, WHERE'S THE DOE'S HARD ESTIMATE ON THE SSC?
The DOE was supposed to reconcile four cost estimates, ranging from $7.8B to a reported $11.7B, to arrive at an official figure for Congress by 17 Aug (WN 17 Aug 90). Instead DOE asked for a postponement until today; now they say it will be next week. The official line is that they are busy inventing an energy policy. Speculation ranges from efforts to jawbone the ICE group into changing its assumptions, to a desire to quietly slip the report under the door during the confusion as Congress returns.



Bob Park can be reached via email at whatsnew@bobpark.org
THE UNIVERSITY OF MARYLAND
Opinions are the author's and are not necessarily shared by the University, but they should be.